CMAQ IV - Phase 2E (Congestion Mitigation and Air Quality): Proposed improvements for CMAQ 4 Phase 2E include traffic signal modifications and intersection improvements on Beltway 8 frontage road between West Gulf Bank and T.C. Jester. Joint participation project between Harris County and the Texas Department of Transportation.

(Last Updated On 3/14/2019)

Proposed improvements include upgrading Boudreaux Road, between Telge Road and Rocky Road, as a 4-lane concrete pavement section with appropriate drainage. The project is currently in the Study Phase.

(Last Updated On 3/14/2019)

Planned improvements include upgrading Champions Drive from a 2-lane asphalt roadway to a 2-lane concrete pavement section with an improved drainage system. Commissioners Court awarded the Project to Allgood Construction Co., Inc. and Notice to Proceed with the construction efforts was issued for September 24, 2018. The Project is expected to be complete on April 5, 2020, barring any unforeseen circumstances beyond the Contractor's control (i.e., inclement weather). This is a Joint Participation project between Harris County Precinct 4 and Champions Municipal Utility District.

(Last Updated On 3/14/2019)

Proposed improvements include widening and extending Cypress North Houston Rd (formerly Lou Edd Rd) as a 4-lane concrete pavement section with an appropriate drainage system, traffic signal installations at Misty Moss Dr, Autumn Mills Dr, and FM 1960, and all appurtenances necessary for a complete project. The project is currently in the Design phase. It is Harris County's goal to bid the project for construction upon completion of project development (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 3/14/2019)

Precinct 4 has partnered with Precinct 3 to extend Cypress Rose Hill Rd, within Precinct 4's jurisdiction from north of FM 2920 to approximately 1,500’ north of FM 2920, in conjunction with Precinct 3’s Cypress Rose Hill Rd capital improvement project. The new section of roadway will transition into existing Decker Prairie Rosehill Road. Planned improvements include the extension, within the limits described, as a 4-lane concrete boulevard section with appropriate drainage and a west connection to Waller Tomball Rd. The Project is currently in the Design Phase and it is Harris County's goal to bid the project for construction in 2nd quarter 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 3/14/2019)

Proposed improvements include the installation of a warranted traffic signal system on Cypress Station Dr at Hollow Tree Ln. The project is currently in the Design Phase and it is Harris County's goal to issue Notice to Proceed with the construction efforts in the 3rd quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 3/14/2019)

CMAQ IV - Phase 1B (Congestion Mitigation and Air Quality): Planned improvements include the installation of new traffic signals and intersections improvements on Cypresswood Drive at: Lockridge Dr, Whitewood Dr, Spring Mill Ln, Breckenridge Forest Dr, Homestead Pass Dr, Monteith Dr, Maplegate Dr, and Hickory Twig Way; Modifications to the battery back-up systems on Cypresswood Dr at: Aldine Westfield Rd, Birnamwood Blvd, James C. Leo Dr, Quailgate Dr, Coachgate Dr, Lynnegate Dr, and Cypresswood Point Ave; Signal rebuild, geometric improvements, and modifications to battery back-up systems on Cypresswood Drive at Holzwarth Rd; TxDOT modifications and geometric improvements on Cypresswood Drive at IH-45; Extension of the westbound left turn lane, modifications to the battery back-up system on Cypresswood Drive at Old Cypresswood Dr/Bradbury Forest Dr; Installation of a southbound left turn lane on Cypresswood Dr at Oaklynn Dr; Extension of the northbound left turn lane and southbound left turn lane on Cypresswood Drive at Treaschwig Rd; and Signal rebuild and modifications to the battery back-up system on Cypresswood Dr at Cypresswood Dr E/Cypresswood Dr W. Commissioners Court awarded the Project to Main Lane Industries and Notice to Proceed was issued for February 11, 2019. Construction completion is scheduled for June 5, 2020 (barring any unforeseen circumstances beyond Harris County's control). Joint participation project between Harris County and the Texas Department of Transportation.

(Last Updated On 3/14/2019)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Drive at Breckenridge Forest Drive. The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Drive corridor.

(Last Updated On 3/22/2018)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Drive at Hickory Twig Way. The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Dive corridor.

(Last Updated On 3/22/2018)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Drive at Homestead Pass Drive. The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Drive corridor.

(Last Updated On 3/22/2018)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Drive at Lockridge Drive. The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Drive corridor.

(Last Updated On 3/22/2018)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Drive at Monteith Drive. The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Drive corridor.

(Last Updated On 3/22/2018)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Drive at Spring Mill Lane. The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Drive corridor.

(Last Updated On 3/22/2018)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Drive at Whitewood Drive. The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Drive corridor.

(Last Updated On 3/22/2018)

CMAQ 4 - Phase 2D (Congestion Mitigation and Air Quality): Proposed improvements include traffic signal modifications and intersection improvements on the SH 249 frontage road between Antoine and Spring Cypress. Phase 2D also includes traffic signal modifications and intersection improvements on FM 529 between North Eldridge Pkwy and Greenhouse. Joint participation project between Harris County and the Texas Department of Transportation.

(Last Updated On 3/14/2019)

Proposed improvements include extending Gessner Rd as a 4-lane concrete pavement section with appropriate drainage. The project is currently in the Design Phase.

(Last Updated On 3/14/2019)

Proposed improvements include upgrading Gleannloch Forest from a 2-lane concrete boulevard to a 4-lane concrete boulevard. The project is currently in the Bid/Award Phase. Joint Participation project between Harris County Municipal Utility Districts 367 & 383 and Harris County Precinct 4.

(Last Updated On 3/14/2019)

Planned improvements include widening Gosling Rd to a 4-lane concrete boulevard section with an appropriate drainage system and all appurtenances necessary for a complete project. Commissioners' Court awarded the Project to Allgood Construction and Notice to Proceed was issued March 21, 2018. Construction completion is scheduled for the 4th quarter 2019 (barring any unforeseen circumstances beyond Harris County’s control).

(Last Updated On 3/14/2019)

Proposed improvements include widening Gosling Road to a 4-lane concrete boulevard section with an appropriate drainage system and all appurtenances necessary for a complete project. The Project is currently in the Design phase. It is Harris County's goal to bid the Project for construction purposes in the 2nd quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 3/14/2019)

Proposed improvements include the installation of a warranted traffic signal system on Gosling Road at Root Road. The project is currently in the Design Phase and it is Harris County's goal to issue Notice to Proceed with the construction effort in 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 8/16/2018)

Proposed improvements include the addition of a of a twin bridge over Spring Creek. The project is currently in the Study Phase. Joint Participation Proejct between Harris County Precinct 4 and Montgomery County Precinct 3.

(Last Updated On 3/14/2019)

Proposed improvements include upgrading Grant Rd to a 4-lane concrete pavement section with appropriate drainage. The project is currently in the Study Phase.

(Last Updated On 3/14/2019)

Proposed imporvements include upgrading Grant Rd to a 4-lane concrete pavement section with appropriate drainage. The project is currently in the Study Phase.

(Last Updated On 3/14/2019)

Proposed imporvements include upgrading Grant Road, between Telge Road and Shaw Road, as a 4-lane concrete pavement section with appropriate drainage. The project is currently in the Study Phase.

(Last Updated On 8/24/2018)

Planned improvements include extending Holderrieth Rd as a 4-lane concrete boulevard section with appropriate drainage and all appurtenances necessary for a complete project. Commissioners Court awarded the Project to Unitas Construction and the Contractor was given Notice to Proceed on January 29, 2018. Construction completion is scheduled for the second quarter of 2019 (barring any unforeseen circumstances beyond Harris County’s control).

(Last Updated On 3/14/2019)

Proposed improvements include upgrading Holderrieth Rd to a 4-lane concrete pavement section with appropriate drainage system. The project is currently in the Study Phase.

(Last Updated On 3/14/2019)

Proposed improvements include extending Holderrieth Rd to a 4-lane concrete pavement section with appropriate drainage system. The project is currently in the Study Phase.

(Last Updated On 3/14/2019)

Proposed improvements to Hufsmith Rd include the addition of a secondary Burroughs Park access road, intersection improvements, and geometric and traffic signal modifications as warranted. The project is currently in the Design phase. It is Harris County's goal to bid the Project for construction purposes in the 1st quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 3/14/2019)

Proposed improvements include upgrading Hufsmith-Kohrville Rd to a 4-lane concrete pavement section with appropriate drainage system, traffic signalization at Lacey Rd and at Ezekiel Rd, as warranted, and all appurtenances necessary for realizing a complete project. The Project is currently in the Design phase and it is Harris County's goal to bid the Project for construction purposes in the 2nd quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 3/14/2019)

Proposed improvements include upgrading Hufsmith-Kohrville Rd to a 4-lane concrete pavement section with appropriate drainage system, traffic signalization at Woodland Shore Dr, as warranted, and all appurtenances necessary for realizing a complete project. The Project is currently in the Design phase and it is Harris County's goal to bid the Project for construction purposes in 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 3/14/2019)

Proposed improvements include upgrading Hufsmith-Kohrville Rd to a 4-lane concrete pavement section with appropriate drainage system, traffic signals or traffic signal modifications as warranted and all appurtenances necessary for realizing a complete project. The project is currently in the Study phase.

(Last Updated On 3/14/2019)

Planned improvements include upgrading Hufsmith-Kohrville Rd from the existing 2-lane asphalt roadway to a 4-lane concrete boulevard section with storm sewer system, traffic signal installation at Mahaffey Road, as warranted ,and all appurtenances necessary for realizing a complete project. The Project was awarded to Allgood Construction and Notice to Proceed was given January 29, 2018. The Project is expected to be complete in the first quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 3/14/2019)

Planned improvements included widening the half-boulevard section of Kings Park Way (Atasca Oaks Drive) to a 4-lane concrete boulevard section with appropriate drainage accommodations, traffic signal modifications and all appurtenances necessary for a complete project. Notice to Proceed with the construction efforts was given for September 4, 2018. Project was deemed substantially complete on November 21, 2018. This was a Joint Participation effort between Precinct 4 and Precinct 2.

(Last Updated On 12/3/2018)

Proposed improvements include upgrading Lockwood Rd from the existing 2-lane asphalt roadway to a 4-lane concrete boulevard section with appropriate drainage system accommodating low impact development components. The Project is currently in the Design phase. It is Harris County's goal to bid the project for construction in the 2nd quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 3/14/2019)

Proposed improvements include the extension of Louetta Rd, from Stablewood Farms in Precinct 3 to Telge Rd in Precinct 4, as a 4-lane concrete pavement section including twin bridges over Little Cypress Creek. The project is currently in the Study Phase. Joint Participation Project between Harris County Precinct 4 and Harris County Precinct 3.

(Last Updated On 3/14/2019)

Proposed improvements include the installation of a warranted traffic signal system on Louetta Road at Strack Drive. The project is currently in the Design Phase and it is Harris County's goal to issue Notice to Proceed with the construction effort in the 2nd quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 2/18/2019)

Proposed improvements improving Nabors Pkwy (formerly Humble Road), between Calvert Rd and SH 249, as a 2-lane concrete pavement section with appropriate drainage. The project is currenty in the Design Phase. It is Harris County's goal to advertise the project for construction purposes in the 2nd quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 3/14/2019)

Proposed imporvements include upgrading Neuens Rd from a 2-lane asphalt roadway to a 2-lane concrete pavement section with appropriate drainage. The project is currently in the Study Phase. Joint Participation Project between Harris County Precicnt 4 and the CIty of Houston.

(Last Updated On 3/14/2019)

Proposed improvements include widening North Eldridge Pkwy to a 4-lane concrete boulevard section with an appropriate drainage system. The Project is currently in the Design Phase and it is Harris County's goal to bid the project for construction in the 4th quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 3/14/2019)

CMAQ IV - Phase IC (Congestion Mitigation and Air Quality): Planned improvements include the installation of new traffic signals and intersection improvements on North Eldridge Pkwy at: Firebrick Dr, Castlebridge Dr, Normont Dr, Quail Creek Dr, Chriswood Dr, New Hampton Dr/Lakewood Villa Dr, Guernsey Dr; Modifications to the battery back-up systems on North Eldridge Pkwy at: W Little York, Emmett Rd, Chimney Sweep Dr, Taylor, Crossroads Park Dr, Malcomson Rd, and Louetta Rd; Modifications to the battery back-up systems, loops, and pedestrian push button upgrades on North Eldridge Pkwy at: Lakes on Eldridge/Twin Lakes Blvd and West Rd; Signal rebuild on North Eldridge Pkwy at Tanner Road; Northbound left turn lane on North Eldridge Pkwy at Crossridge Dr; and Extension of northbound and southbound turn lanes on North Eldridge Pkwy at FM 1960. The Project is in the Bid/Award Phase. Joint participation project between Harris County and the Texas Department of Transportation.

(Last Updated On 3/14/2019)

Proposed improvements include the installation of a warranted traffic signal on North Eldridge Parkway at Castlebridge Drive. The improvements are part of the CMAQ Phase 1C project which includes traffic signal modifications and intersection improvements for various intersections along the North Eldridge Parkway corridor.

(Last Updated On 8/25/2016)

Proposed improvements include the installation of a warranted traffic signal on North Eldridge Parkway at Chriswood Drive. The improvements are part of the CMAQ Phase 1C project which includes traffic signal and intersection improvements for various intersections along the North Eldridge Parkway corridor.

(Last Updated On 8/25/2016)

Proposed improvements include the installation of a warranted traffic signal on North Eldridge Parkway at Firebrick Drive. The improvements are part of the CMAQ Phase 1C project which includes traffic signal modifications and intersection improvements for various intersections along the North Eldridge Parkway corridor.

(Last Updated On 8/25/2016)

Proposed improvements include the installation of a warranted traffic signal on North Eldridge Parkway at Guernsey Drive. The improvements are part of the CMAQ Phase 1C project which includes traffic signal modifications and intersection improvements for various intersections along the North Eldridge Parkway corridor.

(Last Updated On 8/25/2016)

Proposed improvements include the installation of a warranted traffic signal on North Eldridge Parkway at New Hampton/Lakewood Villa Drive. The improvements are part of the CMAQ Phase 1C project which includes traffic signal modifications and intersection improvements for various intersections along the North Eldridge Parkway corridor.

(Last Updated On 8/25/2016)

Proposed improvements include the installation of a warranted traffic signal on North Eldridge Parkway at Normont Drive. The improvements are part of the CMAQ Phase 1C project which includes traffic signal and intersection improvements for various intersections along the North Eldridge Parkway corridor.

(Last Updated On 8/25/2016)

Proposed improvements include the installation of a warranted traffic signal on North Eldridge Parkway at Quail Creek Drive. The improvements are part of the CMAQ Phase 1C project which includes traffic signal modifications and intersection improvements for various intersections along the North Eldridge Parkway corridor.

(Last Updated On 8/25/2016)

Proposed improvements include upgrading Riley Fuzzel Rd from the existing 2-lane asphalt roadway to a 5-lane concrete pavement section with appropriate drainage system, and all appurtenances necessary for realizing a complete project. The project is currently in the Design phase and is expected to be published for bidding purposes in the 4th quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 3/14/2019)

CMAQ 4 - Phase 2D (Congestion Mitigation and Air Quality): Proposed improvements include traffic signal modifications and intersection improvements on the SH 249 frontage road between Antoine and Spring Cypress. Phase 2D also includes traffic signal modifications and intersection improvements on FM 529 between North Eldridge Pkwy and Greenhouse. Joint participation project between Harris County and the Texas Department of Transportation.

(Last Updated On 3/14/2019)

CMAQ IV - Phase 2F (Congestion Mitigation and Air Quality): Proposed improvements for CMAQ 4 Phase 2F include traffic signal modifications and intersection improvements on the SH 6 corridor from West Little York to West Road. Phase 2F also includes traffic signal modifications and intersection improvements on the FM 1960 corridor between Fallbrook Drive and Kenswick Drive. Joint participation project between Harris County and the Texas Department of Transportation.

(Last Updated On 3/14/2019)

Improvements included the installation of a warranted traffic signal system on Spears Road at River Laurel Drive. Construction was completed on January 29, 2019 and the traffic signal is now fully operational. This is a Joint Participation Project between Harris County Precinct 1 and Harris County Precinct 4.

(Last Updated On 2/18/2019)

CMAQ IV - Phase IA (Congestion Mitigation and Air Quality): Proposed improvements include: Installation of new traffic signals and intersection improvements on Spring Cypress Road at: Chaseloch St, Glenn Haven Estates Dr, Carrot St./Stone Forest Dr, and Foster Road; Modifications to battery back-up systems on Spring Cypress Road at: Telge Rd, Louetta Rd, Village Creek Trail, North Eldridge Parkway, Hufsmith-Kohrville Rd, Cutten Rd, Doerre Rd, T.C. Jester Blvd, and Kuykendahl Rd; Signal modification and modifications to the battery back-up systems on Spring Cypress Road at: Gleannloch Lakes Blvd, Ella Blvd and Normandy Forest; Signal modifications, modifications to the battery back-up systems, and intersection improvements on Spring Cypress Road at: Champion Forest Dr and Stuebner Airline Dr; and fiber drop-ins on Spring Cypress at Old Louetta/Memorial Falls Dr. Commissioners Court awarded the Project to Third Coast Services and Notice to Proceed was issued for March 11, 2019. Construction completion is scheduled for June 3, 2020 (barring any unforeseen circumstances beyond Harris County's control). Joint participation project between Harris County and the Texas Department of Transportation.

(Last Updated On 3/14/2019)

Proposed improvements include the installation of a warranted traffic signal on Spring Cypress Road at Carrot Street / Stone Forest Drive. The improvements are part of the CMAQ 4 Phase 1A project which includes traffic signal and intersection improvements for various intersections along the Spring Cypress Road corridor.

(Last Updated On 8/25/2016)

Proposed improvements include the installation of a warranted traffic signal on Spring Cypress Road at Chaseloch Street. The improvements are part of the CMAQ 4 Phase 1A project which includes traffic signal modifications and intersection improvements for various intersections along the Spring Cypress Road corridor.

(Last Updated On 11/8/2016)

Proposed improvements include the installation of a warranted traffic signal on Spring Cypress Road at Foster Road. The improvements are part of the CMAQ 4 Phase 1A project which includes traffic signal modifications and intersection improvements for various intersections along the Spring Cypress Road corridor.

(Last Updated On 2/1/2017)

Proposed improvements include the installation of a warranted traffic signal on Spring Cypress Road at Glenn Haven Estates Drive. The improvements are part of the CMAQ 4 Phase 1A project which includes traffic signal modifications and intersection improvements for various intersections along the Spring Cypress Road corridor.

(Last Updated On 8/25/2016)

Proposed improvements include the installation of a warranted traffic signal system on Spring Cypress Road at Senterra Lakes Boulevard. The project is currently in the Design Phase and it is Harris County's goal to issue Notice to Proceed with the construction effort in the 2nd quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 2/18/2019)

Proposed improvements include extending Stuebner Airline Rd as a 4-lane concrete pavement section with an appropriate drainage system and all components necessary for a complete project. The Project is currently in the Study Phase.

(Last Updated On 3/14/2019)

Proposed improvements include the installation of a warranted traffic signal system on Tanner Road at Cunningham Road. The project is currently in the Design Phase and it is Harris County's goal to issue Notice to Proceed with the construction effort in the 2nd quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 2/18/2019)

Planned improvements include widening Telge Road as a 4-lane concrete boulevard section with an appropriate drainage system. Commissioners Court awarded the Project to SER Construction Partners, Ltd. and Notice to Proceed with the construction efforts was issued for October 10, 2018. The Project is expected to be complete on October 14, 2019, barring any unforeseen circumstances beyond the Contractor's control (i.e., inclement weather).

(Last Updated On 3/14/2019)

Proposed improvements include widening Telge Rd as a 4-lane concrete boulevard section with appropriate drainage system, traffic signalization at Grant Road, and all appurtenances necessary for a complete project. The Project is currently in the Design Phase and it is Harris County's goal to bid the project for construction in the 3rd quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 3/14/2019)

Proposed improvements include widening Telge Rd as a 4-lane concrete boulevard section with appropriate drainage system. The project is currently in the Design Phase.

(Last Updated On 3/14/2019)

Proposed improvements include widening Telge Rd as a 4-lane concrete boulevard section with appropriate drainage system. The Project is currently in the Design Phase.

(Last Updated On 3/14/2019)

Proposed improvements include upgrading Treaschwig Rd from the existing 2-lane asphalt roadway to a 4-lane concrete boulevard section with appropriate drainage system, traffic signalization at Trilby Way, and all appurtenances necessary for realizing a complete project. The Project is currently in the Design phase and it is Harris County's goal to advertise the project for construction purposes in the 2nd quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 3/14/2019)

Proposed improvements include the installation of a warranted traffic signal system on West Little York Road at Westminster Village Drive. The project is currently in the Design Phase and it is Harris County's goal to issue Notice to Proceed with the construction effort in the 3rd quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 2/18/2019)

Planned improvements include widening Wilson Road as a 4-lane concrete boulevard section with appropriate drainage system, traffic signalization at Greens Road, the installation of a sidewalk extension between Humble ISD - Park Lakes Elementary property line and Viscaro Lane, and all appurtenances necessary for a complete project. The Project was awarded to SER Construction Partners, Ltd and the contractor was given Notice to Proceed on January 29, 2018. The Project is expected to be complete October 21, 2019 (barring any unforeseen circumstances beyond the Harris County’s control).

(Last Updated On 3/14/2019)

Proposed improvements include the installation of a warranted traffic signal system on Woodland Hills Drive at Liles Lane. The project is currently in the Design Phase and it is Harris County's goal to issue Notice to Proceed with the construction effort in the 1st quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 2/18/2019)