CMAQ IV - Phase 2E (Congestion Mitigation and Air Quality): Beltway 8 from West Gulf Bank Rd to TC Jester Blvd Planned improvements for CMAQ 4 Phase 2E include traffic signal modifications and intersection improvements along the Beltway 8 frontage road between West Gulf Bank Rd and TC Jester Blvd. The Texas Department of Transportation accepted construction bids for CMAQ 4 - Phase 2D, 2E and 2F on March 6, 2019 and awarded the construction contract to Main Lane Industries. Notice to Proceed with was issued on August 13, 2019 with a completion date of March 2022. Joint participation project between Harris County and the Texas Department of Transportation.

(Last Updated On 9/10/2019)

Proposed improvements include upgrading Boudreaux Rd, from Telge Rd to Rocky Rd, to a 4-lane concrete pavement section with improved drainage accommodations. *Proposed alignment for illustration purposes only*

(Last Updated On 9/16/2019)

Planned improvements include upgrading Champions Dr, from FM 1960 to Cypress Creek, from a 2-lane asphalt roadway to a 2-lane concrete pavement section with an improved drainage system. Commissioners Court awarded the Project to Allgood Construction Co., Inc. and Notice to Proceed with the construction efforts was issued for September 24, 2018. The Project is expected to be complete by April 5, 2020, barring any unforeseen circumstances beyond the Contractor's control (i.e., inclement weather). This is a Joint Participation project between Harris County Precinct 4 and Champions Municipal Utility District.

(Last Updated On 6/26/2019)

Planned improvements include widening and extending Cypress North Houston Rd (formerly Lou Edd Rd), from Jones Rd to FM 1960, as a 4-lane concrete pavement section with improved drainage accommodations and traffic signal installations at Misty Moss Dr, Autumn Mills Dr, and FM 1960. The project is currently in the Design phase and Harris County will bid the Project for construction upon completion of project development. *Proposed alignment for illustration purposes only*

(Last Updated On 9/12/2019)

Precinct 4 has partnered with Precinct 3 to upgrade Cypress Rose Hill Rd, within Precinct 4's jurisdiction, from FM 2920 to approximately 1,500’ north of FM 2920, in conjunction with Precinct 3’s Cypress Rose Hill Rd capital improvement project. The new section of roadway will transition into existing Decker Prairie Rosehill Rd. Planned improvements include the extension, within the limits described, as a 4-lane concrete boulevard section with appropriate drainage and a west connection to Waller-Tomball Rd. The Project is currently in the Design Phase and Harris County will bid the project for construction upon completion of project development. *Proposed alignment for illustration purposes only*

(Last Updated On 9/12/2019)

Planned improvements include the installation of a warranted traffic signal system on Cypress Station Dr at Hollow Tree Ln. The project is currently in the Design Phase and it is Harris County's goal to issue Notice to Proceed with the construction efforts in the 4th quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 9/9/2019)

CMAQ IV - Phase 1B (Congestion Mitigation and Air Quality): Cypresswood Dr Corridor from Hickory Twig Way to Cypresswood Point Ave Planned improvements include: The installation of new traffic signals and intersections improvements on Cypresswood Dr at: Lockridge Dr, Whitewood Dr, Spring Mill Ln, Breckenridge Forest Dr, Homestead Pass Dr, Monteith Dr, Maplegate Dr, and Hickory Twig Way; Modifications to the battery back-up systems on Cypresswood Dr at: Aldine Westfield Rd, Birnamwood Blvd, James C. Leo Dr, Quailgate Dr, Coachgate Dr, Lynnegate Dr, and Cypresswood Point Ave; Signal rebuild, geometric improvements, and modifications to battery back-up systems on Cypresswood Dr at Holzwarth Rd; TxDOT modifications and geometric improvements on Cypresswood Dr at IH-45; Extension of the westbound left turn lane, modifications to the battery back-up system on Cypresswood Dr at Old Cypresswood Dr/Bradbury Forest Dr; Installation of a southbound left turn lane on Cypresswood Dr at Oaklynn Dr; Extension of the northbound left turn lane and southbound left turn lane on Cypresswood Dr at Treaschwig Rd; and Signal rebuild and modifications to the battery back-up system on Cypresswood Dr at Cypresswood Dr E/Cypresswood Dr W. Commissioners Court awarded the Project to Main Lane Industries and Notice to Proceed was issued for February 11, 2019. Construction completion is scheduled for June 5, 2020 (barring any unforeseen circumstances beyond Harris County's control). Joint participation project between Harris County and the Texas Department of Transportation.

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Dr at Breckenridge Forest Dr. The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Dr corridor. Commissioners Court awarded the Project to Main Lane Industries and Notice to Proceed was issued for February 11, 2019. Construction completion is scheduled for June 5, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Dr at Hickory Twig Way. The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Dr corridor. Commissioners Court awarded the Project to Main Lane Industries and Notice to Proceed was issued for February 11, 2019. Construction completion is scheduled for June 5, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Dr at Homestead Pass Dr. The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Dr corridor. Commissioners Court awarded the Project to Main Lane Industries and Notice to Proceed was issued for February 11, 2019. Construction completion is scheduled for June 5, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Dr at Lockridge Dr. The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Dr corridor. Commissioners Court awarded the Project to Main Lane Industries and Notice to Proceed was issued for February 11, 2019. Construction completion is scheduled for June 5, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Dr at Maplegate Dr. The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Dr corridor. Commissioners Court awarded the Project to Main Lane Industries and Notice to Proceed was issued for February 11, 2019. Construction completion is scheduled for June 5, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Dr at Monteith Dr . The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Dr corridor. Commissioners Court awarded the Project to Main Lane Industries and Notice to Proceed was issued for February 11, 2019. Construction completion is scheduled for June 5, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Dr at Spring Mill Ln. The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Dr corridor. Commissioners Court awarded the Project to Main Lane Industries and Notice to Proceed was issued for February 11, 2019. Construction completion is scheduled for June 5, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on Cypresswood Dr at Whitewood Dr. The improvements are part of the CMAQ 4 Phase 1B project which includes traffic signal modifications and intersection improvements for various intersections along the Cypresswood Dr corridor. Commissioners Court awarded the Project to Main Lane Industries and Notice to Proceed was issued for February 11, 2019. Construction completion is scheduled for June 5, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

CMAQ 4 - Phase 2D (Congestion Mitigation and Air Quality): FM 529 Corridor between Greenhouse Rd and North Eldridge Pkwy Planned improvements include traffic signal modifications and intersection improvements on FM 529 between Greenhouse Rd and North Eldridge Pkwy. Phase 2D also includes traffic signal modifications and intersection improvements on SH 249 between Antoine Rd and Spring Cypress Rd. The Texas Department of Transportation accepted construction bids for CMAQ 4 - Phase 2D, 2E and 2F on March 6, 2019 and awarded the construction contract to Main Lane Industries. Notice to Proceed with was issued on August 13, 2019 with a completion date of March 2022. Joint participation project between Harris County and the Texas Department of Transportation.

(Last Updated On 9/10/2019)

Proposed improvements include extending Gessner Rd, from West Rd to Fallbrook Dr, as a 4-lane concrete pavement section with improved drainage accommodations. The project is currently in the Design Phase and Harris County will bid the project for construction upon completion of project development. *Proposed alignment for illustration purposes only*

(Last Updated On 9/12/2019)

Improvements included upgrading Gleannloch Forest Dr, from 1400' south of SH 99 to SH 99, from a 2-lane concrete road to a 4-lane concrete boulevard. The roadway was opened to 4 lanes the first week of September 2019. Joint Participation project between Harris County Municipal Utility Districts 367 & 383 and Harris County Precinct 4.

(Last Updated On 9/12/2019)

Improvements include upgrading Gosling Rd, from Mossy Oaks Rd to W Rayford Rd, to a 4-lane concrete boulevard section with an improved drainage system. Commissioners' Court awarded the Project to Allgood Construction and construction completion is scheduled for 1st quarter 2020, barring any unforeseen circumstances beyond Harris County’s control (i.e., inclement weather, etc.).

(Last Updated On 6/26/2019)

Proposed improvements include upgrading Gosling Rd, from W Rayford Rd to Creekside Forest Dr, to a 4-lane concrete boulevard section with improved drainage accommodations and traffic signal installation/modification as warranted. The Project is currently in the Design phase and Harris County will bid the project for construction upon completion of project development. *Proposed alignment for illustration purposes only*

(Last Updated On 9/12/2019)

Planned improvements include the installation of a warranted traffic signal system on Gosling Rd at Root Rd. The project is currently in the Design Phase and it is Harris County's goal to issue Notice to Proceed with the construction effort in the 4th quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 9/9/2019)

Proposed improvements include widening Gosling Rd, from Creekside Forest Dr in Harris County Precinct 4 to Gatewood Reserve Ln in Montgomery County Precinct 3, as a 4-lane concrete pavement section and the addition of a two-lane bridge over Spring Creek. The project is currently in the Study Phase. Joint Participation Project between Harris County Precinct 4 and Montgomery County Precinct 3. *Proposed alignment for illustration purposes only*

(Last Updated On 9/16/2019)

Proposed improvements include upgrading Grant Rd, from Spring Cypress Rd to Shaw Rd, as a 4-lane concrete pavement section with improved drainage accommodations and traffic signal installation/modification as warranted. The project is currently in the Study Phase. *Proposed alignment for illustration purposes only*

(Last Updated On 9/16/2019)

Proposed imporvements include upgrading Grant Rd, from Telge Rd to Shaw Rd, to a 4-lane concrete pavement section with improved drainage accommodations and traffic signal installation/modifications as warranted. The project is currently in the Study Phase. *Proposed alignment for illustration purposes only*

(Last Updated On 9/16/2019)

Proposed improvements include upgrading Grant Rd, from Cypress Rosehill Rd to Telge Rd, as a 4-lane concrete pavement section with improved drainage accommodations and traffic signal installation/modification as warranted. *Proposed alignment for illustration purposes only*

(Last Updated On 9/16/2019)

Improvements included the extension of Holderrieth Rd, from east of Calvert Rd to SH 249, as a 4-lane concrete boulevard section with appropriate drainage and all components necessary for a complete project. The roadway was opened to the public on September 9, 2019 and construction efforts will continue until the Contractor completes remaining work items. The project is expected to be fully complete within the coming weeks.

(Last Updated On 9/12/2019)

Proposed improvements include upgrading Holderrieth Rd, from SH 249 to Hufsmith-Kohrville Rd, as a 4-lane concrete pavement section with improved drainage accommodations and traffic signal installation/modifications as warranted. The project is currently in the Study Phase. *Proposed alignment for illustration purposes only*

(Last Updated On 9/16/2019)

Proposed improvements include extending Holderrieth Rd, from Hufsmith-Kohrville Rd to SH 99 at Champion Forest Dr, as a 4-lane concrete pavement section with improved drainage accommodations and traffic signal installation/modification as warranted. The project is currently in the Study Phase. *Proposed alignment for illustration purposes only*

(Last Updated On 9/16/2019)

Planned improvements include upgrading Hufsmith Rd, between Burroughs Park and Lakes at Creekside Dr, the addition of a secondary Burroughs Park access road, intersection improvements, and geometric and traffic signal modifications as warranted. The project is currently in the Design phase and Harris County will bid the project for construction upon completion of project development. *Proposed alignment for illustration purposes only*

(Last Updated On 9/12/2019)

Proposed improvements include upgrading Hufsmith-Kohrville Rd to a 4-lane concrete pavement section with appropriate drainage system, traffic signalization at Woodland Shore Dr, as warranted, and all appurtenances necessary for realizing a complete project. The Project is currently in the Design phase and Harris County will bid the project for construction upon completion of project development. *Proposed alignment for illustration purposes only*

(Last Updated On 9/12/2019)

Planned improvements include upgrading Hufsmith-Kohrville Rd, between Hollow Glen Ln and Ezekiel Rd, as a 4-lane concrete pavement section with improved drainage accommodations, traffic signalization at Lacey Rd and at Ezekiel Rd, as warranted, and all components necessary for realizing a complete project. The Project is currently in the Design phase and Harris County will bid the project for construction upon completion of project development. **Proposed alignment for illustration purposes only*

(Last Updated On 9/12/2019)

Proposed improvements include upgrading Hufsmith-Kohrville Rd, between Holderrieth Rd and Mahaffey Rd, as a 4-lane concrete pavement section with improved drainage accommodations, traffic signal installation/modification as warranted, and all components necessary for a complete project. The project is currently in the Study phase. *Proposed alignment for illustration purposes only*

(Last Updated On 9/16/2019)

Planned improvements include upgrading Lockwood Rd, from the Union Pacific Railroad to Beltway 8, from the existing 2-lane asphalt roadway to a 4-lane concrete boulevard section with an improved drainage system accommodating low impact development components. The Project is currently in the Design phase and Harris County will bid the project for construction upon completion of project development. *Proposed alignment for illustration purposes only*

(Last Updated On 9/12/2019)

Proposed improvements include the extension of Louetta Rd, from Stablewood Farms Dr in Precinct 3 to Telge Rd in Precinct 4, as a 4-lane concrete pavement section including twin bridges over Little Cypress Creek and improved drainage accommodations. The project is currently in the Design Phase. Joint Participation Project between Harris County Precinct 4 and Harris County Precinct 3. *Proposed alignment for illustration purposes only*

(Last Updated On 9/16/2019)

Improvements included upgrading Strack Dr to a 3-lane pavement section at Louetta Rd, and the installation of a warranted traffic signal system on Louetta Rd at Strack Dr. Construction of the improvements was completed on August 29, 2019, and the traffic signal is now fully operational.

(Last Updated On 9/9/2019)

Planned improvements include upgrading Nabors Pkwy (formerly Humble Rd), between Holderrieth Rd and SH 249, as a 2-lane concrete pavement section with improved drainage accommodations. The project is currenty in the Design Phase and Harris County will bid the project for construction upon completion of project development. *Proposed alignment for illustration purposes only*

(Last Updated On 9/12/2019)

Proposed imporvements include upgrading Neuens Rd, from Gessner Rd to Blalock Rd, from a 2-lane asphalt roadway to a 2-lane concrete pavement section with improved drainage accommodations. The project is currently in the Design Phase. Joint Participation Project between Harris County Precinct 4 and the CIty of Houston. *Proposed alignment for illustration purposes only*

(Last Updated On 9/16/2019)

Proposed improvements include widening North Eldridge Pkwy, from Spring Cypress Rd to Westlock Dr, to a 4-lane concrete boulevard section with improved drainage accommodations and traffic signalization at Westlock Drive and Gregson Road. The Project is currently in the Design Phase and Harris County will bid the project for construction upon completion of project development. *Proposed alignment for illustration purposes only*

(Last Updated On 9/12/2019)

CMAQ IV - Phase IC (Congestion Mitigation and Air Quality): North Eldridge Pkwy Corridor from Clay Rd to Spring Cypress Rd Planned improvements include: The installation of new traffic signals and intersection improvements on North Eldridge Pkwy at: Firebrick Dr, Castlebridge Dr, Normont Dr, Quail Creek Dr, Chriswood Dr, New Hampton Dr/Lakewood Villa Dr, Guernsey Dr; Modifications to the battery back-up systems on North Eldridge Pkwy at: W Little York, Emmett Rd, Chimney Sweep Dr, Taylor, Crossroads Park Dr, Malcomson Rd, and Louetta Rd; Modifications to the battery back-up systems, loops, and pedestrian push button upgrades on North Eldridge Pkwy at: Lakes on Eldridge/Twin Lakes Blvd and West Rd; Signal rebuild on North Eldridge Pkwy at Tanner Road; Northbound left turn lane on North Eldridge Pkwy at Crossridge Dr; and Extension of northbound and southbound turn lanes on North Eldridge Pkwy at FM 1960. Commissioners Court awarded the Project to MBN Enterprises and Notice to Proceed was issued for April 8, 2019. Construction completion is scheduled for March 22, 2020 (barring any unforeseen circumstances beyond Harris County's control). Joint participation project between Harris County and the Texas Department of Transportation.

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on North Eldridge Pkwy at Castlebridge Dr. The improvements are part of the CMAQ Phase 1C project which includes traffic signal modifications and intersection improvements for various intersections along the North Eldridge Pkwy corridor. Commissioners Court awarded the Project to MBN Enterprises and Notice to Proceed was issued for April 8, 2019. Construction completion is scheduled for March 22, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on North Eldridge Pkwy at Chriswood Dr. The improvements are part of the CMAQ Phase 1C project which includes traffic signal and intersection improvements for various intersections along the North Eldridge Pkwy corridor. Commissioners Court awarded the Project to MBN Enterprises and Notice to Proceed was issued for April 8, 2019. Construction completion is scheduled for March 22, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on North Eldridge Pkwy at Firebrick Dr. The improvements are part of the CMAQ Phase 1C project which includes traffic signal modifications and intersection improvements for various intersections along the North Eldridge Pkwy corridor. Commissioners Court awarded the Project to MBN Enterprises and Notice to Proceed was issued for April 8, 2019. Construction completion is scheduled for March 22, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on North Eldridge Pkwy at Guernsey Dr. The improvements are part of the CMAQ Phase 1C project which includes traffic signal modifications and intersection improvements for various intersections along the North Eldridge Pkwy corridor. Commissioners Court awarded the Project to MBN Enterprises and Notice to Proceed was issued for April 8, 2019. Construction completion is scheduled for March 22, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on North Eldridge Pkwy at New Hampton Dr/Lakewood Villa Dr. The improvements are part of the CMAQ Phase 1C project which includes traffic signal modifications and intersection improvements for various intersections along the North Eldridge Pkwy corridor. Commissioners Court awarded the Project to MBN Enterprises and Notice to Proceed was issued for April 8, 2019. Construction completion is scheduled for March 22, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on North Eldridge Pkwy at Normont Dr. The improvements are part of the CMAQ Phase 1C project which includes traffic signal and intersection improvements for various intersections along the North Eldridge Pkwy corridor. Commissioners Court awarded the Project to MBN Enterprises and Notice to Proceed was issued for April 8, 2019. Construction completion is scheduled for March 22, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Planned improvements include the installation of a warranted traffic signal on North Eldridge Pkwy at Quail Creek Dr. The improvements are part of the CMAQ Phase 1C project which includes traffic signal modifications and intersection improvements for various intersections along the North Eldridge Pkwy corridor. Commissioners Court awarded the Project to MBN Enterprises and Notice to Proceed was issued for April 8, 2019. Construction completion is scheduled for March 22, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Proposed improvements include upgrading Riley Fuzzel Rd, from Elm St to Hardy Toll Rd, from the existing 2-lane asphalt roadway to a 5-lane concrete pavement section with improved drainage accommodations, realigning Riley Fuzzel Rd to remove the sharp turns in the roadway, the closure of the railroad crossing at Caroline St and the opening of a new crossing north of Riley Fuzzel Rd. The project was published for bid in September 2019. The Bid and Award phase typically takes 90-120 to accomplish. *Proposed alignment for illustration purposes only*

(Last Updated On 9/12/2019)

CMAQ 4 - Phase 2D (Congestion Mitigation and Air Quality): SH 249 from Antoine Rd to Spring Cypress Rd Planned improvements include traffic signal modifications and intersection improvements along the SH 249 frontage road between Antoine Rd and Spring Cypress Rd. Phase 2D also includes traffic signal modifications and intersection improvements on FM 529 between Greenhouse Rd and North Eldridge Pkwy. The Texas Department of Transportation accepted construction bids for CMAQ 4 - Phase 2D, 2E and 2F on March 6, 2019 and awarded the construction contract to Main Lane Industries. Notice to Proceed with was issued on August 13, 2019 with a completion date of March 2022. Joint participation project between Harris County and the Texas Department of Transportation.

(Last Updated On 9/10/2019)

CMAQ IV - Phase 2F (Congestion Mitigation and Air Quality): SH 6 Corridor from West Little York Rd to West Rd and FM 1960 Corridor from Fallbrook Dr to Kenswick Dr Planned improvements include traffic signal modifications and intersection improvements along the SH 6 corridor from West Little York Rd to West Rd, and the FM 1960 corridor between Fallbrook Dr to Kenswick Dr. The Texas Department of Transportation accepted construction bids for CMAQ 4 - Phase 2D, 2E and 2F on March 6, 2019 and awarded the construction contract to Main Lane Industries. Notice to Proceed with was issued on August 13, 2019 with a completion date of March 2022. Joint participation project between Harris County and the Texas Department of Transportation.

(Last Updated On 9/10/2019)

CMAQ IV - Phase IA (Congestion Mitigation and Air Quality): Spring Cypress Rd Corridor from Telge Rd to Louetta Glen Dr Planned improvements include: Installation of new traffic signals and intersection improvements on Spring Cypress Rd at: Chaseloch St, Glenn Haven Estates Dr, Carrot St/Stone Forest Dr, and Foster Rd; Modifications to battery back-up systems on Spring Cypress Rd at: Telge Rd, Louetta Rd, Village Creek Trail, North Eldridge Pkwy, Hufsmith-Kohrville Rd, Cutten Rd, Doerre Rd, T.C. Jester Blvd, and Kuykendahl Rd; Signal modification and modifications to the battery back-up systems on Spring Cypress Rd at: Gleannloch Lakes Blvd, Ella Blvd and Normandy Forest Dr; Signal modifications, modifications to the battery back-up systems, and intersection improvements on Spring Cypress Rd at: Champion Forest Dr and Stuebner Airline Dr; and fiber drop-ins on Spring Cypress Rd at Old Louetta Rd/Memorial Falls Dr Commissioners Court awarded the Project to Third Coast Services and Notice to Proceed was issued for March 11, 2019. Construction completion is scheduled for June 3, 2020 (barring any unforeseen circumstances beyond Harris County's control). Joint participation project between Harris County and the Texas Department of Transportation.

(Last Updated On 4/26/2019)

Proposed improvements include the installation of a warranted traffic signal on Spring Cypress Rd at Carrot Rd / Stone Forest Dr. The improvements are part of the CMAQ 4 Phase 1A project which includes traffic signal and intersection improvements for various intersections along the Spring Cypress Rd corridor. Commissioners Court awarded the Project to Third Coast Services and Notice to Proceed was issued for March 11, 2019. Construction completion is scheduled for June 3, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Proposed improvements include the installation of a warranted traffic signal on Spring Cypress Rd at Chaseloch St. The improvements are part of the CMAQ 4 Phase 1A project which includes traffic signal modifications and intersection improvements for various intersections along the Spring Cypress Rd corridor. Commissioners Court awarded the Project to Third Coast Services and Notice to Proceed was issued for March 11, 2019. Construction completion is scheduled for June 3, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Proposed improvements include the installation of a warranted traffic signal on Spring Cypress Rd at Foster Rd . The improvements are part of the CMAQ 4 Phase 1A project which includes traffic signal modifications and intersection improvements for various intersections along the Spring Cypress Rd corridor. Commissioners Court awarded the Project to Third Coast Services and Notice to Proceed was issued for March 11, 2019. Construction completion is scheduled for June 3, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Proposed improvements include the installation of a warranted traffic signal on Spring Cypress Rd at Glenn Haven Estates Dr. The improvements are part of the CMAQ 4 Phase 1A project which includes traffic signal modifications and intersection improvements for various intersections along the Spring Cypress Rd corridor. Commissioners Court awarded the Project to Third Coast Services and Notice to Proceed was issued for March 11, 2019. Construction completion is scheduled for June 3, 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 6/26/2019)

Improvements included the installation of a warranted traffic signal system on Spring Cypress Rd at Senterra Lakes Blvd. Construction of the improvements was completed on August 28, 2019, and the traffic signal is now fully operational.

(Last Updated On 9/9/2019)

Planned improvements include the installation of a warranted traffic signal system on Stuebner Airline Rd at Farm League Park.

(Last Updated On 9/9/2019)

Proposed improvements include extending Stuebner Airline Rd, from FM 2920 to SH 99, as a 4-lane concrete pavement section with an improved drainage system and all components necessary for a complete project. The Project is currently in the Study Phase. *Proposed alignment for illustration purposes only*

(Last Updated On 9/16/2019)

Planned improvements include upgrading Cunningham Rd to a 3-lane pavement section at Tanner Rd, and the installation of a warranted traffic signal system on Tanner Rd at Cunningham Rd. The project is currently in the Design Phase and it is Harris County's goal to issue Notice to Proceed with the construction effort in the 3rd quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 9/9/2019)

Improvements included widening Telge Rd, from Spring Cypress Rd to north of Louetta Rd, from a 2-lane asphalt roadway to a 4-lane concrete boulevard section with an improved drainage system. The project was deemed complete in August 2019.

(Last Updated On 8/13/2019)

Proposed improvements include widening Telge Rd, from north of Louetta Rd to north of Grant Rd, as a 4-lane concrete boulevard section with an improved drainage system, traffic signalization at Grant Rd, and all components necessary for a complete project. The Project is currently in the Design phase and Harris County will bid the project for construction upon completion of project development. *Proposed alignment for illustration purposes only*

(Last Updated On 9/12/2019)

Proposed improvements include widening Telge Rd, from north of Grant Rd to north of SH 99, as a 4-lane concrete boulevard section with an improved drainage system, traffic signalization at Kitzman Rd and Boudreaux Rd as warranted, and all components necessary for a complete project. The project is currently in the Design Phase. *Proposed alignment for illustration purposes only*

(Last Updated On 9/16/2019)

Proposed improvements include widening Telge Rd, from north of SH 99 to FM 2920, as a 4-lane concrete boulevard section with an improved drainage system. The Project is currently in the Design Phase. *Proposed alignment for illustration purposes only*

(Last Updated On 9/16/2019)

Planned improvements include upgrading Treaschwig Rd, from Aldine Westfield Rd to Birnam Wood Blvd, from the existing 2-lane asphalt roadway to a 4-lane concrete boulevard section with an improved drainage system, traffic signalization at Trilby Way, and all components necessary for a complete project. The Project is currently in the Design phase Harris County will bid the project for construction upon completion of project development. *Proposed alignment for illustration purposes only*

(Last Updated On 9/12/2019)

Planned improvements include the installation of a warranted traffic signal system on West Little York Rd at Westminster Village Dr. The project is currently in the Design Phase and it is Harris County's goal to issue Notice to Proceed with the construction effort in the 4th quarter of 2019 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 9/9/2019)

Planned improvements include the installation of a warranted traffic signal system on West Rd at Greens Crossing Blvd. The project is currently in the Design Phase and it is Harris County's goal to issue Notice to Proceed with the construction effort in 2020 (barring any unforeseen circumstances beyond Harris County's control).

(Last Updated On 9/9/2019)

Improvements included widening Wilson Rd, from Beltway 8 to Atascocita Rd, as a 4-lane concrete boulevard with an improved drainage system, traffic signalization at Greens Rd, the installation of a sidewalk extension between Humble ISD - Park Lakes Elementary property line and Viscaro Ln, and all components necessary for a complete project. The Project was deemed complete in August 2019.

(Last Updated On 8/13/2019)

Improvements included the installation of a warranted traffic signal system on Woodland Hills Dr at Liles Ln. Construction of the improvements was completed on July 2, 2019, and the traffic signal is now fully operational.

(Last Updated On 9/9/2019)